We have a specific requirement at my client. We plan both Finished and Semi finished products for PPDS in APO. Every week the PPDS plan will be freezed for the week 3 weeks ahead and will not revisit this again.
The requirement is when we run heuristics after the plan is freezed (for 3 weeks in future), is there any way to restrict heuristics not to create Recipts for the Requirements falling in 1st 3 weeks period (which is freezed). I tried with planning time fence, but heuristics reads the requirements from today itself and create Receipts after the 3 weeks period (which I updated 21 days as PPDS planning time fence).
Please suggest if there is any way to restrict heuristics not to read the requirements at all for 3 weeks from today.